Sequence Dependency Setup and Logic
Hi,
i was trying to do basic test cases for the sequence dependent functionality in OPM integration with ASCP. Initially i created the sequence dependent class category and assigned two sub assembly items to sequence dependency class category. In the routing on the items i checked the sequence dependent box and in the process planning i assigned operations with their setup time.In resource the schedule to instance and SDS days are introduced.Finally i assigned both the sub assemblies
For example : To change operation A in item 1 to operation B in item 2, i need 5 hours and vice versa i.e to change operation B in item 2 to operation A in item 1, i need same 5 hours.
1