Resource UOM setup
We are using BOM,WIP and ASCP and have a question on the unit of measure setup for Resource.
a) Resource is setup to include in the Routing,which is used to calculate the Cost as well as capacity on ASCP.
Lets say an Item requires 0.5Hrs of this resource usage and cost of that operation is 7USD
b) If we setup the resource UOM as Hour and assign a standard cost of 1USD, then
1) Routing operation-> Resource usage of 0.5 will mean to complete the operation, Resource required is =0.5hrs. ASCP plan can consider this and no issues there.