HI,
In WORK process first Operation is OSP.

After releasing the JOB system is created Requisition and user created a PO using auto create form.

material shifter to the Vendor against 57F4 challan.

Now OSP vendor Misplaced the raw material.

Now i hve to raise a Debit Note OSP vendor for the misplaced the raw material and i have to issue a new

material to complete the job.

Kindly provide suggestions/solution to resolve the issue.