I have a set of activities that i need to display per week, the activity description is: Jetgrouting 6 off Columns and i create a UDF and populate it with the number values in the activcity description like 6, some activity description have different number of columns ranging from 3,4, 6, 11, 12 etc and the overall total in the UDF is 2679. I needed to find out how many columns is constructed per week.
There are three different construction machines making these columns, they called Rigs 1, 2 and 3 they are coded so i associate each line of activity to that Rig but i was hoping to be able to display a spreadsheet out of P6 to tell me how many columns is constructed per week and what Rig is being used.
There are three different construction machines making these columns, they called Rigs 1, 2 and 3 they are coded so i associate each line of activity to that Rig but i was hoping to be able to display a spreadsheet out of P6 to tell me how many columns is constructed per week and what Rig is being used.