Estimate to Complete Distribution
When a curve is assigned to a resource assignment, it would distribute the budgeted and remaining units/costs per time interval based on that curve. However, the Estimate to Complete values (where ETC is not equal to remaining value) does not distribute the values based on curve, just linear. Is there a way to distribute ETC values based on a curve assigned to a resource assignment? Please advise.
Thanks, Nick