Multipe Men on a Resource
How do I depict multipe person(s) on the same resource. For example I have a 160 hour activity with a 5 day duration. I know I will have 4 Carpentar's work 8 hours a day each for 5 days. Is there a column where I can depict 4/8 on the resources tab?