When set to Accrue on Receipt, we don't see invoice price variance posting to Projects
1. Change PO flag to Accure on Receipt
2. Enter Requisition for $500k
3. Approve PO and create receipt for $100k
4. Run Interface Supplier Cost and Update Project Summary. See Commitment for the 500k and Actuals of 100k.
5. Create invoice of $101k and match to PO from step #3. Validated and created accounting for the invoice.
6. Run Interface Supplier cost and Update Project Summary and we don't see the invoice variance of $1k.