Resolved - The data date is displayed as the early and late start and finish for all completed activ
I finally figured this out. I had forgotten to select Progress Override when I did the final update. I think Progress Override should be the default and I figured this wild bite me in the butt sooner or later. Retained logic does not conform to reality and I really don't see why anyone would want to use under ordinary circumstances.
I have a schedule for a completed project that I must submit to a government agency on Monday. The job is 100% complete but the data date is displayed as the early and late start and finish dates for every activity in the project. These fields should be blank for completed activities.
I have a schedule for a completed project that I must submit to a government agency on Monday. The job is 100% complete but the data date is displayed as the early and late start and finish dates for every activity in the project. These fields should be blank for completed activities.