I finally figured this out. I had forgotten to select Progress Override when I did the final update. I think Progress Override should be the default and I figured this wild bite me in the butt sooner or later. Retained logic does not conform to reality and I really don't see why anyone would want to use under ordinary circumstances.
I have a schedule for a completed project that I must submit to a government agency on Monday. The job is 100% complete but the data date is displayed as the early and late start and finish dates for every activity in the project. These fields should be blank for completed activities.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center