OPM Costing - Percentage Overheads Based on Resource
Our overheads are calculated based on resource usage. The % varies based on the department or resouce. Unfortunately it does not appear that we can use resource, or resource class even as a priority when defining the overhead percentages. Every priority is either Organization or Item related. Our items are produced using multiple resources, in multiple departments and it does not look like I can manage the % overhead this way. Any ideas would be greatly appreciated.
We are on Standard Costing.
0