OP integration with MSP 2007

Dear all,Regarding the integration between oracle projects and MSP 2007...In MSP when in Assign resource to a task and enter his daily work hours (work pattern) randomly such as Sat:8h, Sun:6h, Mon:2h etc, I sent them successfully to oracle BUT After receiving them again back to MSP it spread them as flat Sat:4h, Sun:4h, Mon:4h etc,  this spread make me lose my resources allocation for multi tasks !! So I re-entered their time again.