MRP R3483 and Work Order Cutt off status (as stated in Proccess Options of P48013)
Hi to all.
We are advancing in our manufacturing floor control and mrp implementation, and we are facing the issue that we are receiving messages for Work Orders that have passed the cutt off status as stated in P48013 processing options.
Is there any way to prevent the generation of messages for work orders beyond a specified status?
ie:
we have setup 41 as our cutt off status (for us 41 = Firm Planned Order)
If we dont wat to receive messages for orders with status equal or greater than 41, is there any way?
We also tried with the freeze planing days, but seems that the system is using required date vs mrp generation date as the days, and we are receiving messages for orders that have start date within the freeze fence, but required date beyond the fence (we already have started these work orders).
We are advancing in our manufacturing floor control and mrp implementation, and we are facing the issue that we are receiving messages for Work Orders that have passed the cutt off status as stated in P48013 processing options.
Is there any way to prevent the generation of messages for work orders beyond a specified status?
ie:
we have setup 41 as our cutt off status (for us 41 = Firm Planned Order)
If we dont wat to receive messages for orders with status equal or greater than 41, is there any way?
We also tried with the freeze planing days, but seems that the system is using required date vs mrp generation date as the days, and we are receiving messages for orders that have start date within the freeze fence, but required date beyond the fence (we already have started these work orders).
0