PRC: Update Project Summary Amounts and multiple operating units
We have two operating units. We run PRC: Update Project Summary Amounts, and because the process automatically enters the operating unit of the responsibility, we can only run it for one operating unit at a time. So I did some research and found out about the Operating Unit Mode property. I changed this property value from Single to null, and then to Multiple. Regardless of what I set the Operating Unit Mode property to, the concurrent request only processes the Operating Unit of the responsibility.
We also run PRC: Update Project and Resource Base Summaries, and PRC: Update Project Performance Data. Both of these concurrent programs will calculate for both Operating Units in one request, using the same responsibility as we run PRC: Update Project Summary Amounts with.