EPPM P6R8.2 - Summarize Project Fail - Expense Budget Field blank
While summarizing projects I had one fail with:
Error ??EXCEPTION: com.primavera.summarizer.SummarizerException:Failed calculating field rollups for project 4546 and wbs ids [26203, 26210]??
Error ??EXCEPTION: com.primavera.summarizer.SummarizerException:Failed calculating field rollups for project 4546 and wbs ids [26203, 26210]??
The Oracle Knowledgebase recommended running a query to the NEXTKEY table (https://support.oracle.com/epmos/faces/DocumentDisplay?id=1537706.1). Didn't work.
I narrowed it down to an activity that had expenses loaded and found one that the Budget Cost field was blank. I put in 0 and it summarized like a charm.