Suggestions for mapping following requirement;
Item A is FG
Item B & C are raw materials which will be sent outside for processing
Item A's routing is as follows
OpNo Op Code
10 OSP1 (Raw materials A & B will be sent to supplier X for OSP from Shopfloor)
20 DRIL (Raw materials A & B will be returned to Shopfloor)
30 OSP2 (Raw materials A & B will be sent to supplier Y for OSP from Shopfloor)
40 OSP3 (Raw materials A & B will be sent to supplier Z for OSP from supplier Y)