 Suggestions for mapping following requirement;
Item A is FG
Item B & C are raw materials which will be sent outside for processing
Item A's routing is as follows

OpNo   Op Code
10     OSP1 (Raw materials A & B will be sent to supplier X for OSP from Shopfloor)
20     DRIL (Raw materials A & B will be returned to Shopfloor)
30     OSP2 (Raw materials A & B will be sent to supplier Y for OSP from Shopfloor)
40     OSP3 (Raw materials A & B will be sent to supplier Z for OSP from supplier Y)

Regards