Baseline Funding button on Funding Inquiry - not available if navigating from the Agreement Screen
My client does not enter a Revenue Budget so we are using the Baseline Funding function available on the Funding Inquiry screen to create the revenue budget and baseline it. For some reason, in R12.1.3, if I navigate to the screen from the button on the Agreement screen, the Baseline Funding button is not available. If I navigate there by going back to the menu, it is available and works fine.
Anyone else faced with this problem and put a fix in place?
Appreciate suggestions. My client wants to customize the screen so it works.
Best regards,
Bob
0