Vu asks:
We have applied number of patches (see uploaded file) and most of them took too long to complete.
Our system cannot be down for 30-40 hours to apply these patches.
We need to know why? and  resolution for them.

If we need to merge them then should we merge them all or merge them by group of patches?


The time I have in uploaded file is the processing time only.
This time does not include trouble shooting or administration time.
Our PROD system can not be down this long to apply these patches.

We want to have a solution to optimize applied processing time.
Tagged:

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center