edited Jun 27, 2013 5:47AM in Primavera (MOSC) 6 commentsAnswered ✓
How can I transfer relationships from my original project to a modified copy of the project that doesn't include those relationships?  The original activities still include the same Act ID and Description, but other data may have been updated and new activities have been added with no logic ties.