Planning Options Definition and Rate Schedules
I defined a Rate Schedule and enter the rates applicable to employees: Employee A -> $100 Employee B -> $80
When defining the Planning Options for an Approved Cost Budget in the Rate Schedule Options is mandatory to select a Rate Schedule defined by Resource Class
I don't have the option to select the Rate Schedule defined by Employees.
To continue with my plan type definition I created another Rate Schedule for the Resource Class: People and added a rate, then I completed the Planning Options and enter the budget amounts by Employee as per my requirement.
The system took as rate the ones specified in the Rate Schedule define by Employee (as I want)