PO/Receipts not showing in Projects Commitment
I'm working on this projects issue and wondering if someone could provide a solution to this:
PO 489483 contains lines for Project FE2013-0046 Task 4.20.43.02.02.
PO Line 1 has quantity ordered = 45
PO Line 2 has quantity ordered = 5
Receipt 190177 has been created for PO Line 1 and 2
Issue is => These amounts, on Receipt 190177 above, are nowhere to be found on the Project, neither as a Commitment nor an Expense. Our thinking was, since these Items have not yet been Delivered on the Receipt, they should still be a Commitment on the Project. As is the case in other similar situations
We created a SR and Oracle’s Response: