Copy schedule without changing activity ID's
Just upgraded from 6.2 to 8.3 and ready to update a schedule for the 1st time. I always copy/paste a schedule and then change the Project ID to reflect the new data date before updating. I need to run claim digger after the update to document all the changes from the last update. When I click paste it has three options for changing the Activity ID's with no option for leaving them as is. If the ID's change I can't run a comparison to the baseline or previous updates not to mention will totally mess up the coding system used for