R04570 and Discount CutOff
Hi,
Posted on behalf of customer:
Enter voucher in P0411 with payment term in 30 days, 8 discount days, invoice date= 1/5, DDJ = 9/5, DDNJ=31/5.
Create automatic payment with R04570. It seems that the PO 3. Discount Cutoff Date of R04570 looks at DDJ, while I would expect it to be the discount due date as the PO mentions.
- if enter in the PO 8/5 it does take discount
- if enter in the PO 10/5 it does NOT take discount
Question 1: Is this analysis correct:
Question 2: If there are no Bug fixes (see Bug 10719044) than how to select the vouchers that are due to pay, while the real DDJ is wrong?