Min Manx Replineshment Purchase Requisition based on the Demand Cut Off Date ??
Hope you all OK, here me just wanted to know very few things from you such as;
We have setups the the Replineshment Cycle based on the sourcing Rule as b/w two diffrent Orgs A & B.
Whenever User raise the Requisition from Org A and source Organization is Org B and and Need by Date is Todays date. We have schedule the Create Internal Order , Import Order Concurrent on the back hand and the ISO in turn also gets created in turn but the On hand Quantity is not avaible in the ORG B, Now the ORG B User Run the Min Max Planning based on the Demand Cutt Off Date (just above the Requested Date of ISO) with Restock Yes and Submits it accordingly. But the Report of Min Max doesnt showing me any