What is the proper steps for updating a resource's price/unit in mid project

edited May 29, 2013 12:29PM in Primavera (MOSC) 3 commentsAnswered
We updated a resource's price/unit after he obtained his P.Eng. and now all the cost calculation for activities with him involved in is out of wreck (by small amount but still not accurate)eg. this is from a test project I created to do some future weeks to see if the actual cost will stable itself after a couple of weeks after the price/unit is updated
his original rate is $97/hr and new rate is $118/h, updated at the end of week 20

wk units this period cost this period total units total cost 19 10 970 10 970 20 10 970 20 1940 21 10 1033 30 2973 22 10 1207 40 4180 23 10 1223 50 5403 24 10 1205 60 6608 25 10 1196 70 7804 26 10 1192 80 8996 27 10 1189 90 10185 28 10 1177 100 11362
Also for the actual (real)  project, for the week that the resource had 0 (no) units (hours), there is still a $73 charge listed on the actual cost this period column?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center