Unable to compile MRP_RESCHEDULE_PO after ASCP patch 9839214
Hi,
Apps 12.1.3
Customer has applied patch 9839214 during upgrade process of Advanced supply chain planning.
MRP_RESCHEDULE_PO is invalid compiles with following errors.
alter package MRP_RESCHEDULE_PO compile body;Warning: Package Body altered with compilation errors.SQL> show error
Errors for PACKAGE BODY MRP_RESCHEDULE_PO:LINE/COL ERROR
-------- -----------------------------------------------------------------
424/2 PL/SQL: Statement ignored
424/13 PLS-00306: wrong number or types of arguments in call to
'RESCHEDULE'484/8 PL/SQL: Statement ignored
484/19 PLS-00306: wrong number or types of arguments in call to
'RESCHEDULE'
Errors for PACKAGE BODY MRP_RESCHEDULE_PO:LINE/COL ERROR
-------- -----------------------------------------------------------------
424/2 PL/SQL: Statement ignored
424/13 PLS-00306: wrong number or types of arguments in call to
'RESCHEDULE'484/8 PL/SQL: Statement ignored
484/19 PLS-00306: wrong number or types of arguments in call to
'RESCHEDULE'
File versions in
/*$Header: MRPRSPOS.pls 120.0.12010000.3 2010/03/19 18:59:46 cnazarma ship $ */
/*$Header: MRPRSPOB.pls 120.3.12010000.6 2010/07/06 22:50:19 cnazarma ship $ */
/*$Header: MRPRSPOB.pls 120.3.12010000.6 2010/07/06 22:50:19 cnazarma ship $ */
Found Bug 9609421 - QRE1213.1:SCM:MRP.INV.1:INVALID OBJECTS FOUND BY AUTOBUILD