Cost roll up for batch quantity
We are working in E9.1 and need some quick info on cost roll up for batch quantity. Here is the scenario. We have work centers , are being used in different products manufacturing with different batch quantities , with different routing hours/crew size etc. so we have added different crew size , machine/labor hours in corresponding routing definition of the manufactured item. However we did not define the crew size, no of employees & no of machines in each work center . We have frozen only machine and labor rates and adding the overheads thru cost components as X cost.
Can you explain how does cost roll up happen in this case ? Does it take crew size from routing definition or does it from work center definition. I appreciate your valuable inputs.