I have Created the Capital Project with cost types has Burdened for that i have
1. Define Burden Bases, cost codes, Structures and Schedules
2. Created the New Capital Project Types for Burdened cost
3. Created The Template and Projects.
4. Created and assign the assets.
5. Created the Supplier Cost, Pre-approved Costs and Process the Cost to GL
6. CIP Cost was Generated in Capital Project Information
But When i Generate the Asset line for that project then the Output Shows as Blank.
if anybody knows,kindly Provide the Solution to Generate the Asset line.
Regards
Sree
I have Created the Capital Project with cost types has Burdened for that i have
1. Define Burden Bases, cost codes, Structures and Schedules
2. Created the New Capital Project Types for Burdened cost
3. Created The Template and Projects.
4. Created and assign the assets.
5. Created the Supplier Cost, Pre-approved Costs and Process the Cost to GL
6. CIP Cost was Generated in Capital Project Information
But When i Generate the Asset line for that project then the Output Shows as Blank.
if anybody knows,kindly Provide the Solution to Generate the Asset line.
Regards
Sree
0