    I have been using Primavera for a couple years now. However, when I was first trained on the software I recall the instructor advising of the benefits of using SS and FF relationships, and that when scheduling the project, if the Start milestone is initiated the successor activity will automatically get statused as "Started" and if all predecessors linked to a Finish Milestone with FF relationships would be automatically updates as Finished.       Is this concept familiar to anyone? Where is this functionality located in the software?   Over a year ago I noticed that this feature was no longer working