Must finish by date

edited Jun 19, 2013 10:13AM in Primavera (MOSC) 3 commentsAnswered
I'm reviewing a programme in P6.1 with a project must finish by date. This is creating a bit of negative float.

Deleting the must finish by date however leaves a critical path that does not cover the duration of the project.

What could be the cause of this.

I'm using Total float = 0 as my critical path definition?