Must finish by date
I'm reviewing a programme in P6.1 with a project must finish by date. This is creating a bit of negative float.
Deleting the must finish by date however leaves a critical path that does not cover the duration of the project.
What could be the cause of this.
I'm using Total float = 0 as my critical path definition?