WIP MASS LOAD failing with error "Missing shift information on resources" though the shifts are corr
We are facing the issue where WIP MASSS LOAD is failing with error as "Missing shift information on resources" though the shifts are correctly defined.
We have checked the shift foer these resources, but its correctly defined. The WIP jobs are released through MRP.
As per the Metalink note - Define Discrete Job WIPDJMDF form Err Missing shifts or shift times for resource [ID 455679.1], we have checked but it seems that this resources are added for this item through same ECO. But we are not sure it this was copied from some other assembly item where this resource id disabled.