Sourcing Rule based on Requisition Creation Date and not Need-by date
Let say the following:
· lead time for item xx-01 is 30 days
· item xx-01 is min-max planned
· ASL, Assignment set exist for the item with the following sourcing rule:
o From July 1st to July 31st take supplier Hewitt and BPA 1005
o From August 1st to August 31st take supplier Sandvick and BPA 1009
Scenario:
Today July 4, I run the min-max and import the requisition. Because of the long lead time (30 days) the Need-by date onto the requisition is in August. Hence, Oracle selects Sandvick and its associated BPA.