Using TimeControl with Primavera P6

edited Jul 11, 2013 10:00AM in Primavera (MOSC) 2 commentsAnswered
Have a few issues came up when we are implementing TimeControl (TC) with P6 during our testing phase and would like to ask if any settings in TC or P6 that we can change to correct them.


1) When there is a negative adjustment to the units for a resource that has gone over budget, the remaining units for the resource would became whatever the negative adjustment is rather than stay at 0.
 eg. budget unit = 40, actual unit = 50, remaining unit = 0
An adjustment was made through TC, -5 units was put in TimeControl, the updated units in P6 are as follows:
budget unit = 40, actual unit = 45, remaining unit = 5

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center