Using TimeControl with Primavera P6
Have a few issues came up when we are implementing TimeControl (TC) with P6 during our testing phase and would like to ask if any settings in TC or P6 that we can change to correct them.
1) When there is a negative adjustment to the units for a resource that has gone over budget, the remaining units for the resource would became whatever the negative adjustment is rather than stay at 0.
eg. budget unit = 40, actual unit = 50, remaining unit = 0
An adjustment was made through TC, -5 units was put in TimeControl, the updated units in P6 are as follows:
budget unit = 40, actual unit = 45, remaining unit = 5
1) When there is a negative adjustment to the units for a resource that has gone over budget, the remaining units for the resource would became whatever the negative adjustment is rather than stay at 0.
eg. budget unit = 40, actual unit = 50, remaining unit = 0
An adjustment was made through TC, -5 units was put in TimeControl, the updated units in P6 are as follows:
budget unit = 40, actual unit = 45, remaining unit = 5