FSGBU Primavera Issue | Automatic reset of Project Start date
We are facing an issue in Primavera where in, the planned start dates for the activities are getting automatically set to the project’s Data date.
When we are applying Actuals for the projects, we are setting the new data date with the current date, so that the actual efforts (PR timesheet based) are getting updated in Primavera as on date. But, this date is getting updated as the start date for all the ‘Not started’ activities of the project whenever Actuals are applied, overwriting the original Planned start dates for the activities. With this, not only the start dates are overwritten, but the assigned resources are unable to enter the timesheets for these activities (for previous week).