P6 resources Histgrams
With all live projects open I would expect that the resource profiles would be identical for options "Display: Open Projects only" and "Disply All Projects" (Because I have all Live projects open).
- How can I be sure that the profile is not identifying resouce in the closed and Scenario schduleswhen option "Display All Projects is selected"?
- Can P6 tell me which projects a particular resource is being used on?
- If so can it also tell me the periods it is being used?
I know I can use filters but I want to be able to check what projects resources have been assigned to given the above issue