Hi,
I have one Resource "Furnace" having Per Hour Rate of Rs.10 and Overhead per Hour rate of Rs.100 
Assembly A, B & C each requires 40 Hrs. of Furnace. One furnace can process 100 Assembly numbers at any time.
This resource is included with usage of 40 and basis as Lot in Routing of Assembly A, B & C.

Now if I process 10 quantities of Assembly A Furnace usage cost will be (10*40)+(40*100)

If I process 50 Qty Assembly A, 30 Qty of Assembly B & 20 Qty of Assembly C in Furnace at any time.
Then my actual usage cost is 10*40+100*40=4400
But system is giving cost as 4400+4400+4400=13200

How I can map this requirement of getting correct cost for this resource?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center