P6 EPPM - Problems with projects imported from Microsoft Project
I'm a greenie with Primavera P6 EPPM and am using R8.2. I am having some problems with projects that I imported from Microsoft Project 2010. The "Start" date of an activity that is not yet started is set to the project start date. The activity has a predecessor and a successor, both with the "Relationship Type" of "Finish to Start". The predecessor activity has a date different than the project start date, and is correct. I can change the "Start" and "Finish" dates of the problem activity manually to be correct, but when I run the Scheduler the dates change right