Horizontal Material Plan in MPS Workbench
We are using 11.5.10.2 and using MPS for planning.
We have defined forecast for the item upto 01-Jan-2015 , but if we see the Horizontal Material Plan in MPS workbench for the item, It is showing only upto 01-Aug-2014.
Following steps followed
1)Defined forecast upto 01-Jan-2015
2)MPS> Load Copy merg > used Forecast . Cut off date 01-Aug-2015
3)Launched the MPS > Cut off date 01-Aug-2015
Please advice is there any thing to do cut off date or any set up
Regards