Hi Experts,

I have a Customer with issue, "Job Status of processes in the job console of Planning 11.1.1.3.500 (installed on Microsoft Windows Server 2003 R2 Server 64-bit) are not updating to complete"


What we suggested as a work around is:

1.Backup the HSP_JOB_STATUS table
2. Open the HSP_JOB_STATUS table and locate the job console records which are required to be changed to "Completed"
3. Change the "RUN_STATUS" value of the appropriate records to 2
4. Restart Planning service and Apache HTTP server.

Refer: How to Delete Business Rules Jobs with Status "Processing" in Planning Web? (Doc ID 966683.1)

But customer says that they NEED a permanent SOLUTION.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center