Hi Experts,
Need pointers on product limitation & possible workaround.
Business need:
Client has 5 level of hierarchy in task structure.
They have a strong business need to enforce budgetary control
Budget needs to be controlled at level 2 or 3 or 4 for different task breakdown
Product Limitation:
Based on budget entry method, we can enter budget at Top, Lower or Top & Lower task level only.
if I try to enter budget at level 2/3/4, it is restricted per the budget entry method.
How do we overcome this situation?
with rgds
Muthu
Need pointers on product limitation & possible workaround.
Business need:
Client has 5 level of hierarchy in task structure.
They have a strong business need to enforce budgetary control
Budget needs to be controlled at level 2 or 3 or 4 for different task breakdown
Product Limitation:
Based on budget entry method, we can enter budget at Top, Lower or Top & Lower task level only.
if I try to enter budget at level 2/3/4, it is restricted per the budget entry method.
How do we overcome this situation?