Hello Team,
Can you please advice me on the role of unimplemented ECO in MRP.  I had an item which was marked to be Disabled in the ECO which was unimplemented.
MRP was not calculated the Demand for that item, As soon i implemented the ECO, MRP starting showing the demand for the same item.

Can you please provide some information on this, if unimplemented ECO's do not allow MRP to calculate the demand for the items within ECO.

Note :- Item was being marked to be Disabled in ECO.