Expediting requisitions to existing PO
Hi,
I would like to know if PeopleSoft provides any functionality to expedite the requisitions to an existing PO which is open/Approved but not yet dispatched.
Currently, in PS 9.2, I am not able to find any such option. On the expedite requisition page, I cannot add a PO# to which I would like the req to be added.
In real life scenarios, we are having certain requisitions which need to be added to existing PO since the supplier and schedules are same. But since PeopleSoft does not allow you to expedite to existing PO, we have to create a separate PO for that.