How is the best way to handle percent overlap of routing operations?
Operation 1 - runs for 10 hours.
Operation 2 - starts when Operation 1 is 20 percent complete and then runs for 3 hours.
Operation 3 - starts 1 hours after operation 2 is complete and operation 1 is still running. Operation 3 runs for 2 hours.
We have planned to use Percent Overlap for operations 1 and 2. What is the best way to handle operation 3? We can't use the Percent Overlap because operations 2 and 3 do not overlap - how do we indicate that the overlap is operation 3 and 1?
Thanks