Resource Original Duration is not Equal Activity original duration
Hai
In my Subcontractor submitted Programme some of the Resource Original Duration is not Equal Activity original duration .
This issue occur where single activity have Multiple resource .
Activity Type is task Dependent , Duration type is Fixed Duration & Units /Time, Percentage Complete is duration
Can you say may what is the cause that affect in multiple Resource Assignment Original Duration not equal activity original Duration
Is there any filter to find Where Activity Original Duration is not equal to Resource Assignment Original Duration
Currently I am Organize by Activity in Resource Assignment window with Column Duration & Editing it manually
Thanks
0