Rapid Planning - Manual demands are not considered during simulation
We have issue of manual demands (inserted from backend) are not being considered when we run RP in Incremental Plan mode. The manual demand inserted from backend is a client requirement and we need to find the solution for including the same while we do the simulation.
Below are the steps used by us when we did simulation run in RP. Your valuable feedbacks are highly appreciated.
1) When ‘Manual Demand’ is added from Supply & Demand form, record gets inserted into MSC_DEMANDS.