Way to track labor hours for project transfers?

edited Mar 12, 2016 4:05AM in Discrete Manufacturing - EBS (MOSC) 1 commentAnswered
I posted this in the Projects Community and was advised to post here:

Oracle Applications : 11.5.10.2 - Average costing

Given the following scenario, is there a way to track the number of labor hours contributing to a an item's transferred resource costs?

Using a WIP discrete job for project A, we make 2 cart wheels.  A painter resource spends 1 hour per wheel which is logged as a resource transaction to the job.

The 2 cart wheels are completed into inventory with a cost comprised of the materials and labor.

1 wheel is issued to a WIP job for project B.

1 wheel is issued to a WIP job for project C.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center