Schedule Options - Ignore relationships to and from other projects
Ignore relationships to and from other projects: Mark to ignore activity relationships between projects.
Note
Do not mark this option if you want to preserve activity dates dependent on external relationships to projects that are not in the same database as the project being scheduled.