Scheduling Failed. Cannot Meet Request Date or Latest Acceptable Date: Material Available Date (DD-M
We are on oracle 11.5.10 and at times in Sales Orders we get a note for ATO items at scheduling as
"Scheduling Failed. Cannot Meet Request Date or Latest Acceptable Date: Material Available Date (DD-MON-YY)"
I have checked the ATP Rule setups for the item in question and we are already using the Infinite Supply Option which is set to Cumulative Total Lead Time
Any clue, why we are still getting this Note at the time of Scheduling
Also, fyi the profile option INV:Capable to Promise is set to ATP/CTP Based on Planning Output
Thanks
JM