Recalculate Actual Units and Cost When Duration % Complete Changes

edited Oct 24, 2013 8:28AM in Primavera (MOSC) 2 commentsAnswered
I have an activity with 2 resources.  The first resource is a labor resource with budgeted manhours only (no costs, non-driving).  This resource is merely for showing budgeted manhours per activity.  The second resource is a material resource with specific units and costs per unit.

I would like to use the "Recalculate Actual Units and Cost" for the labor resource only so that the "actual" manhours are updated based on the activity's duration % complete.  However, I do not want the material resource to recalculate based on % complete because the actual units will be updated manually based on actual field quantities.

Is there a way to use the "Recalculate Actual Units and Cost" function for the labor resource, but not the material resource.  It seems that this function, when selected, applies on an "all-or-none" basis regardless of the individual resource's settings.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center