Recalculate Actual Units and Cost When Duration % Complete Changes
I would like to use the "Recalculate Actual Units and Cost" for the labor resource only so that the "actual" manhours are updated based on the activity's duration % complete. However, I do not want the material resource to recalculate based on % complete because the actual units will be updated manually based on actual field quantities.
Is there a way to use the "Recalculate Actual Units and Cost" function for the labor resource, but not the material resource. It seems that this function, when selected, applies on an "all-or-none" basis regardless of the individual resource's settings.