Dear All,
Could you please help us with following scenario.

Created an Assembly (ATO Item) with 2 components.
Created a sales order for the assembly with 3 units.
Progressed the sales order.
The program "AutoCreate Final Assembly Orders" launched and a WIP job created with 3 units to be completed for the assembly.
Did a Component Pick Release and completed the issue of components i.e. L1, L2, L3 of Component 1 and L4,L5 and L6 of Component 2.
Then, built the assembly as LA1, LA2 and LA3 lots.

However, we couldn't drill down to a point where whether LA1 is built with L1 and L4 OR L2 and L5 etc. i.e. which Lots of components have gone into which lots of assemblies. I checked the Lot Genealogy form, but the same is not helpful as it is showing all the 3 lots of component against every lot of assembly.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center