recommend a change to the planned order action message so it will not go over a predetermined maximu
Or as I have outlined below recommend a change to the planned order action message so it will not go over a predetermined maximum. I have safety stock and on order and forecasts.
Will this work?
I am using Available To Promise ATP which is calculated by R3482 and R3483 MRP Generations
UDC 34/QT 97 ATP Available to Promise . . . .
The system calculates the ATP quantity like this:
• First period ATP = on-hand balance − safety stock+ work orders