We have ASCP Consumption questions:

 

Backward/Forward consumption set on forecast set.

Backward Consumption Days: 20

Forward Consumption Days:   40

MSC: Sales Order Offset days = 60 days

 

Forecast Date

Qty

14-OCT-2013

21

 

 

 

Sales Order Number

Schedule Ship Date

Qty

Status

Forecast Consumption

Description

46010809

30-AUG-2013

6

Closed

21-6=15

Not working; why is this sales order not getting consumed?  30-AUG to 14-OCT has 31 work days; our forward consumption is set at 40 days; so this should get consumed; but it is not why? (MRP Consumption works and is consuming this QTY)

46471914

30-SEP-2013

9

Closed

15-9=6

Working

47020324

31-OCT-2013

6

Booked

6-6=0

Working

 

 

Any input would be appreciated.



(Check Attachment -- better format)

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center